防水施工工艺流程
施工工艺:
Construction technology:
1、基层清理干净,原墙地面表面要坚实,不应有起沙、掉灰或空鼓。
1. The base course shall be cleaned up, and the surface of the original wall ground shall be solid without sand, ash or hollowing.
2、对上下水管根部清理并进行堵漏处理。保定平面设计培训 保定空调维修 保定管道通风 包装盒定做 化粪池模具 废旧电缆回收 不锈钢铸件
2. Clean up the roots of the upper and lower water pipes and stop the leakage.
3、用10-15㎜宽美纹纸根据墙面设计施工高度粘贴轮廓线。
3. Use 10-15mm wide masking paper to paste the contour line according to the design and construction height of the wall.
4、第一遍乳液涂刷施工,顺序从上至下,从里到外,不得漏刷。
4, the first time the emulsion brush construction, the order from top to bottom, from inside to outside, do not leak brush.
5、干燥24小时后,涂刷第二遍乳液,使两遍乳液形成完整的防水层。
5. After drying for 24 hours, brush the lotion second times to make the two emulsion form a complete waterproof layer.
6、干燥24小时后,做24小时闭水试验,放水高度不低于30㎜,24小时内无渗漏为合格。
6. After drying for 24 hours, do the 24-hour closed water test, the drainage height is not less than 30 mm, and it is qualified if there is no leakage within 24 hours.
7、表面水泥灰浆拉毛后,可以直接贴砖施工。
7. After the surface cement mortar is roughened, it can be directly tiled.